It's easiest to run a flat down the length of the entire 5mm shaft.
-
The flat only needs to be deep enough for the grub screw to catch and not slip.
-
When your pulleys are in place, be sure to loctite your grub screws.
-
-
-
Add the drive stacks to the printed pieces along with another 20t pulley to lock the stack into place.
-
-
-
Be sure to wire the micro switch as NC (Normally Closed). On most switches this means connecting wires to the outer two terminals on the switch, but you can check with a multimeter by making sure there is continuity at those pins when the switch is not pressed.
-
Add a vertical line to the 20t pulleys in each stack so you can troubleshoot slipping grub screws easily.
-
-
-
The assembly with the micro switch attaches to the right side of the frame.
-
Be sure to run wiring through the channel and be careful to not damage it while tightening.
-
Almost done!
Finish Line